Comprehensive register of 34 Public-Private Partnership concessions, joint ventures, and infrastructure investments facilitated from 2019 to date across transport, commerce, housing, agriculture, and municipal services.
| S/N | PROJECT | IMPLEMENTING MDAs | STATUS / REMARK | COMPANY NAME | PROJECT COST | PROJECT LOCATION | ACTION |
|---|---|---|---|---|---|---|---|
| 1. |
Development of Kontagora Market phase ll
Commerce & Markets
|
Kontagora Local Government
|
In Progress
MOU Signed and the project is in progress
|
Is system Nigeria Ltd.
|
₦1,014,580,094.13 |
Kontagora LGA
|
|
| 2. |
Construction of Mariga Livestock's and produce Market
Agriculture & Livestock
|
Mariga Local Government
|
Revoked / Terminated
MOU Signed on 23r/9/2021 yet to mobilize to site, but advice the Ministry for revocation sincethey breach the agreement of three (3) months in the MOU
|
System Trade and Services Nigeria Ltd.
|
₦9,840,000.00 |
Mariga LGA
|
|
| 3. |
Development of Trailer Park at Mokwa
Transport & Logistics
|
Ministry of Transport
|
Revoked / Terminated
MOU Signed on 23/9/2021 yet to mabilize to site, but advice the Ministry for revocation since they breach the agreement of three (3) months in the MOU
|
Pan Africa Giobal Infrastructure
|
₦5,875,000,000.00 |
Mokwa LG
|
|
| 4. |
Development of Tagina Traiier Park
Transport & Logistics
|
Ministry of Transport
|
Revoked / Terminated
MOU Signed on 23r/9/2021 yet to mobilize to site, but advice the Ministry for revocation since they breach the agreement of three (3) months in the MOU
|
A-Tee Buiiding construction Ltd
|
₦5,551,361,205.10 |
Tagina in Rafi LGA
|
|
| 5. |
Development of Trailer Park along Maje-Dikko road Suleja
Transport & Logistics
|
Ministry of Transport
|
Pending Review
MOU Signed but could not mobilize to site since 2021
|
Bender Park Ltd
|
₦5,514,199,000.94 |
Maje-Dikko road, Suleja LGA
|
|
| 6. |
Development of Dikko Ultra-Modern Market
Commerce & Markets
|
Gurara Local Government
|
Pending Review
Project started in 2018 and stopped in 2019 due to encroachment, presently on crises between the Local Govt.and the investor.
|
El-Kabir Global Bus.Nig. Ltd
|
₦786,113,203.00 |
Dikko, Gurara LGA
|
|
| 7. |
Development of Lambata Trailer Park
Transport & Logistics
|
Gurara Local Government
|
Revoked / Terminated
Award letter issued and MOU Signed but later revoked for non-performance.
|
Susanpauo Nig. Ltd
|
₦4,071,855,712.14 |
Lambata, Gurara Local Government
|
|
| 8. |
Development of Madalla modern Market
Commerce & Markets
|
Suleja LGA / Ministry of Commerce & Industry
|
In Progress
MOU Signed on 25th/3/2019 to be finance 100% by the investor, the project on going.
|
Dodo project consultant Ltd
|
₦5,705,422,422.32 |
Madalla, Suleja LGA
|
|
| 9. |
Housing Project at Jibi
Housing & Real Estate
|
Niger State Housing Corporation (NSHC)
|
In Progress
MOU Signed project on going
|
Brains Hammers Ltd
|
Private Concession Outlay |
Jibi in Suleja LGA
|
|
| 10. |
Development of mini Trailer park at Pago
Transport & Logistics
|
Ministry of Transport
|
Revoked / Terminated
Unserious Investor
|
Susanpauo Nig. Ltd
|
₦4,071,855,712.14 |
Pago, Paikoro LGA
|
|
| 11. |
Development of Shagunu Beach and Resort Centre
Tourism & Hospitality
|
Ministry of Tourism
|
MOU Signed
MOU Signed
|
Marlo Support Services Ltd
|
₦11,651,754,915.10 |
Shagunu in Borgu LGA
|
|
| 12. |
Development IBB International Hospital to international stander
Healthcare
|
Ministry of Health
|
Revoked / Terminated
MOU was initially signed on #20b but later shoot the cost to #50.2billion and the arrangement suspended
|
Rezodonch Group Ltd
|
₦50.2 Billion |
Chanchaga LGA
|
|
| 13. |
Redevelopment of old Lambata Trailer Park to modern market
Commerce & Markets
|
Gurara Local Government
|
MOU Signed
Award letter has been issued and MOU Signed, to be mobilize to site
|
Herris Logistic Service Ltd
|
₦1.6 Billion |
Lambata, Gurara LGA
|
|
| 14. |
Agricultural City Project Tegina
Agriculture & Smart Cities
|
Ministry of Agriculture
|
In Negotiation
Revisited for fresh negotiation
|
All State Resources Management Investment
|
$3,250,000,000.00 |
Tegina, Rafi LGA
|
|
| 15. |
Construction of additional corner shop in IBB Market Suleja
Commerce & Markets
|
Suleja Local Government
|
Pending Review
Awaiting signing of MOU and later obstruct by litigate Staged by market men/women
|
Amach Properties Ltd
|
₦1,730,985,870.00 |
Suleja LGA
|
|
| 16. |
Development of Garatu international Yam and Agriculture Market
Agriculture & Markets
|
Bosso Local Government
|
Revoked / Terminated
MOU Signed but later terminated Unserious Developer (The Investor could not surface again)
|
Investor could not surface again
|
₦900,000,000.00 |
Garatu in Bosso LGA
|
|
| 17. |
Development of Paikoro international Yam Market
Agriculture & Markets
|
Paikoro LGA
|
Revoked / Terminated
MOU Signed but later terminated Unserious Developer (The Investor could not surface again)
|
Investor could not surface again
|
₦900,000,000.00 |
Paikoro in Paikoro LGA
|
|
| 18. |
Concession of Minna/Suleja Water supply project
Water Resources & Utilities
|
Ministry of Water Resources
|
Pending Review
Pending Project (The Investor could not surface again)
|
Investor could not surface again
|
To be determined by investor |
Minna / Suleja
|
|
| 19. |
Construction of Ultra Modern Head Office for Niger State Internal Revenue Services
Public Infrastructure
|
Niger State Internal Revenue Services
|
In Progress
Arrangement concluded, Award letter issued. MOU Signed and the project site been handed over to the investor and has mobilized to site (Work in progress)
|
Larrix Nigeria Limited
|
₦616,224,140.10 |
Minna, Niger State
|
|
| 20. |
Construction of Housing Estate
Housing & Real Estate
|
Niger State Housing Corporation
|
In Negotiation
Negotiation ongoing
|
Black Stone Rical Estate Devt. Ltd
|
In negotiation |
Minna
|
|
| 21. |
Construction of Housing Estate
Housing & Real Estate
|
Niger State Housing Corporation
|
In Negotiation
Negotiation ongoing
|
Pentfield Synergy World Ltd
|
In negotiation |
Minna
|
|
| 22. |
Development of Baro Smart City
Smart Cities & Urban Development
|
SSG / Ministry of Land
|
In Negotiation
Negotiation ongoing
|
Y.G Consult Ltd
|
In negotiation |
Baro / Minna
|
|
| 23. |
Development of old Minna Garage, Suleja into Shopping Complex
Commerce & Markets
|
Suleja Local Government
|
Pending Review
Awaiting stakeholders meeting for further deliberations
|
Duduwa Consult Nig. Ltd
|
₦1,359,880,361.09 |
Suleja
|
|
| 24. |
Construction of mass Housing Estate in Minna Niger State
Housing & Real Estate
|
Niger State Housing Corporation
|
In Negotiation
On negotiation process
|
The Home Group Ltd
|
In negotiation |
Minna, Niger State
|
|
| 25. |
Construction of 1000 Housing Units
Housing & Real Estate
|
Niger State Housing Corporation
|
In Negotiation
On negotiation process
|
Adron Homes and Properties
|
In negotiation |
Minna, Niger State
|
|
| 26. |
Construction of Lambata Trailer Park (estate)
Transport & Logistics
|
Ministry of Transport
|
In Negotiation
On negotiation process
|
Best Petroleum Nig. Ltd
|
In negotiation |
Lambata, Gurara LGA
|
|
| 27. |
Re-Development of Niger Suite in Kaduna
Hospitality & Real Estate
|
Niger State Development Company
|
In Negotiation
On negotiation process
|
Bleet Nig. Ltd
|
In negotiation |
Kaduna
|
|
| 28. |
Establishment of 1,825 metric tons of organic fertilizer processing plant in Suleja
Agriculture & Manufacturing
|
Ministry of Agriculture (MOA)
|
In Negotiation
On negotiation process
|
Alfi Tech Consult Nig. Ltd
|
In negotiation |
Suleja
|
|
| 29. |
Re-Development of Shuaibu Naibi Primary/JSS Suleja to Shopping Mall
Commerce & Markets
|
Suleja LGA
|
In Negotiation
On negotiation process
|
M.N Ataj Construction Ltd
|
In negotiation |
Suleja
|
|
| 30. |
Development of Trailer park
Transport & Logistics
|
Ministry of Transport (MOT)
|
In Negotiation
On negotiation process
|
Birlik Project Nig. Ltd
|
In negotiation |
Mokwa
|
|
| 31. |
Construction of Housing Estate
Housing & Real Estate
|
Niger State Housing Corporation
|
In Negotiation
On negotiation process
|
Ample Innovation Home Ltd
|
In negotiation |
Minna
|
|
| 32. |
Construction of Housing Estate
Housing & Real Estate
|
Niger State Housing Corporation
|
In Negotiation
On negotiation process
|
Tis-Buk Reality Ltd
|
In negotiation |
Suleja
|
|
| 33. |
Development of Cattle Feed Lot in Kateragi Graze Range
Agriculture & Livestock
|
Niger State Livestock & Fisheries Development (NSL&FD)
|
In Negotiation
On negotiation process
|
Sunminners Nig. Ltd
|
In negotiation |
Katerigi, Niger State
|
|
| 34. |
Supply of Buses to Niger State Government on PPP Concept
Transport & Public Mobility
|
PPP Agency / Ministry of Transport
|
In Negotiation
On negotiation process
|
Sanson and Rakiyyat Project Ltd
|
₦2,000,000,000.00 (₦2 Billion) |
Minna
|
Interested in participating in ongoing tenders, proposing an unsolicited concession, or co-investing in transport, agriculture, or municipal infrastructure?